Saturday, August 20, 2016

Abandoned Construction Project due to Sloping Del Rio Clay




Now called the Hope Outdoor Art Gallery, where graffiti "artists" can practice their talents, this site with abandoned concrete slabs and concrete walls and unknown foundation elements was abandoned back in 1985.  This site on Baylor Street in downtown Austin was intended to be office space for high-tech industry professionals.  Instead foundation problems occurred during construction and a dispute between the Developer (Owner) and the General Contractor shut the project down.  The building permit expired in 1987.  The site was purchased by a bank in 1989.  Some demolition of superstructure elements occurred but the at-grade and below-grade elements remain.  This site lies downslope of the "Castle Hill" building (former Texas Military Institute site).  A lawsuit by the Developer was settled out of court and included the Geotechnical Engineer and his firm, Trinity Engineering and Testing Corp (now Kleinfelder) and all other parties on the project team.



Slopes on expansive clay formations are inherently unstable.  I suspect downward slope creep occurred as the project team cut and fill along the slope and applied new surcharge loads.  I do not have any information on the foundation design or as-built foundation data.  The lesson learned is that you develop sloping sites on massive clay soil with extreme caution.











Saturday, August 6, 2016

Do not forget the flatwork





In 2012, less than 2 years after ACC (Austin Community College) opened the new campus in Round Rock, Texas, school officials had to budget $2,000,000 to make repairs associated with expansive clay soils.  Fortunately, most of the problems had to do with the flatwork and not the building.  Too often geotechnical engineers focus attention to the buildings (in this case structurally supported slabs cast on void boxes and constructed on concrete drilled piers) but not enough attention to pavement and flatwork in expansive clay soil environments.

Geotechnical work had been performed by Raba Kistner and architectural detailing by GSC Architects.  Uncertain who were the Structural Engineer and Civil Engineer.

One media source reported that some type of soil improvement was attempted in the flatwork areas (6 feet deep of lime injection possibly?).  However, flatwork (sidewalks) had heaved so severely in some areas that doors could not be opened or closed properly.  Good quality geotechnical reports will address the concern with a structurally supported building slab abutting exterior flatwork.  Sidewalks had to be closed due to tripping hazards.

In 2015 ACC reported that soil movement resulted in surface water (rainwater) entering Building #3000 during heavy rain events.  Heaving and shrinking clay soils will change surface drainage profiles, and both the Geotechnical Engineer and Civil Engineer are responsible for addressing this concern with property owners or developers.

Construction repair bids included one $434,000 proposal to install surface drainage swales, install pedestrian grates over the swale, resurfacing of building flatwork to correct drainage issues, and installation of new stormwater drain along one face of Bldg. 3000.

A photo of sidewalk reconstruction efforts is below.  When you consider the $2,000,000 budget for flatwork and drainage repair, I cannot stress enough how important geotechnical, structural detailing, and civil engineering plan detailing are with regards to flatwork and pavement in expansive clay soil environments.  It starts with the Geotechnical Engineer properly informing the project team of the risks and concerns, and the Civil Engineer and Structural Engineer to formalize final design details.


The purpose of this post is to warn fellow Geotechnical Engineers and Civil Engineers (site grading and drainage) to pay more attention to detail on expansive clay soil environments.  The geotechnical study for this site was probably on the order of $20,000, but omissions of recommendations for dealing with flatwork abutting buildings cost the client $2,000,000 for a $114,000,000 facility.  Ouch.


Saturday, June 1, 2013

COE sues Architectural-Engineering firm for expansive clay damage to utilities

[This case was described in Civil Engineering Magazine in 2013, article written by Michael C. Loulakis.  I have condensed it.]

BPLW Architects and Engineers, Inc. provided the MEP design for two student dorm bldgs at Lackland Air Force Base in San Antonio.  Soon after construction was completed, water leaks occurred that even flooded several rooms.  The US Army Corps of Engineers (COE) repaired the broken pipes and replaced the sanitary sewer pipe system.  The COE billed the MEP firm $7,600,000 for the damages and repair work (negligence or omission claim against the MEP firm).  BPLW appealed to the US Court of Federal Claims.  Heaving clay soils and poor surface drainage design were suspected of having led to the pipe damage and flooding damage.

The "standard of care" requires that the MEP firm consider the geotechnical report ("soils report") when designing underground utilities.  The geotechnical report actually warned that the clay soils at this site could heave 9 inches (i.e. worst case scenario).  The construction contract documents, however, included a mechanical connections section and the MEP firm did abide by the requirements of that section, which apparently included language about tolerating 1 inch of differential movement at horizontal to vertical transitions and possibly 4 inches as the horizontal moves away from a vertical run.  The MEP firm was also accused of producing poor drainage plans (grading and drainage).

The Court determined that the MEP firm's design, as well as its grading plans, failed to comply with the contract and the applicable "standard of care".  But there was also testimony that the GC did not install some of the piping system correctly and that the GC had installed a bent and broken piping component under the slab.  There was uncertainty as to whether the GC had graded the site properly for drainage design (no as-built data).

The Court determined that the COE FAILED TO PROVE CAUSATION.  i.e. the COE did not demonstrate that the design, in contrast to other factors, caused the damage directly.  The COE also did not show that the negligent surface drainage design led to the improper grading and ponding of water.  Poor pipe installation by the GC was the potential intervening cause of damage that allowed the MEP firm to escape this claim.

In addition to failing to prove causation, the COE was also determined by the court to have failed in proving a reasonable damage assessment.  The COE witnesses were not experts and provided insufficient testimony on whether the scope of repair work was reasonable or necessary.  i.e. was that $7,600,000 work all necessary and was that cost reasonable.

The court awarded the COE a small amount of $ for certain modifications it had to make to the MEP's design, but most of the other money was not awarded.  As the prevailing party, the MEP was able to recover money from the COE for legal costs, to make matters worse for the COE.

Lesson learned for geotechs: In cases of negligence claims, the Owner or other suing party has to PROVE CAUSATION.  Even if found having breached the "standard of care", the engineering firm's error has to also be found to have actually directly caused the damage and losses.  If the engineering firm can show that construction errors could have caused soil movement or damage, then causation cannot be linked directly to the design.  Now if the GC performed their duties correctly and installed everything per plans and specs, then your error may indeed be the cause and you simply just need to have your insurance company handle the claim.  Another lesson: geotech should address buried utility construction.  I dont know what was in the geotech report for this site but i am surprised the COE did not sue them for omissions (i.e. lack of recs addressing buried utility construction and connections).  Some will argue the opposite: the less you say, the better.


Sunday, December 2, 2012

Sued for using "dry prep" Atterbergs method

In 2010 a concrete company (and their subconsultant geotechnical firm and construction materials testing lab) was sued by the homeowner.  Their house was exhibiting cracking.  The foundation slab was designed as a post-tensioned slab based on the geotechnical report by Louisiana Testing and Inspection (LTI).  The homeowner chose to sue LTI (via the concrete company that hired them) for failing to identify expansive clay soils and for using the "dry prep" method to perform plasticity lab testing in lieu of the more thorough "wet prep" method.  The wet prep method typically yields a PI a few points higher than the dry prep (i.e. PI=24 instead of 19), which can affect the perception of risk of soil movement as well as the foundation slab design parameter values.

Any lab using the dry prep method can be described as lazy.  I only allow wet prep in my lab.

It turns out that significant stripping and clearing was performed for this lot and subsequent investigation showed some expansive clay was present on the site.  An expert witness geotechnical engineer for the defendant  hypothesized that the Builder filled in a large tree stump and root bulb areas with fat clay, or that the widely spaced borings (1 or 2) simply just missed the zone of expansive clay (most of the site was low PI soils apparently) by pure chance.  The condition was chalked up as an anomalous condition that just did not show up at the drilled (explored) locations (boring logs).  He noted the circular pattern of the swelling condition as validation of the clay backfill theory.  There was no reference to plumbing leak or tests for leaks.

The trial court ruled in favor of the concrete contractor (and LTI) (defendant) because:

- the plaintiff failed to prove that LTI's conduct was the cause-in-fact of the house damage.
- the court found that LTI did not discover the swell potential by pure chance
- the court found that LTI did not improperly report testing.
- the judge found that the plaintiff failed to prove that another design would have been used, and that the swelling would have occurred anyway.

I have a feeling that if i was the expert witness for the homeowner there would have been a better argument for holding the geotech (LTI) responsible (i.e. for poor site characterization and design parameter selection instead of looking at wet prep vs dry prep).  They took the wrong approach by suing based on reported data (lab testing) instead of the overall characterization or design itself, but without more info i cannot really comment intelligently on the case.

The good news for geotechs is the court requires a notable burden on the plaintiff.  The court requires 4 things for a finding of standard negligence:

1. Was the conduct in question a cause-in-fact of the harm that occurred?
2. Did the defendant owe a duty to the plaintiff?
3. Was that duty breached?
4. Was the risk and hard caused within the scope of protection afforded by the duty breached?

LTI got off, but only because the homeowner and their team took a poor approach to this case.  LTI still lost money through the time they had to spend on this case, all for using a dry prep method in the lab.

Sunday, September 23, 2012

Geotechnical study required for all new construction

Here are examples of structural engineers, geotechnical engineers, or other project team members getting into trouble for either not performing a geotechnical study or for being reckless in their inspections or design.  Names of individuals are left out (only initials used) because the point is to learn from these mistakes.  Although companies get to deal with the claim or lawsuit, individual PE's also pay a price to the Texas Board of Professional Engineers (TBPE) (their own wallets opened and license suspended) for mistakes, so never flippantly call an engineer "conservative" or "too safe".

2012: An engineer in Azle, Texas, was suspended (license) by the Board for 4 years and fined $4,380 for "failure to practice engineering in a careful and diligent manner."  A gabion retaining wall he designed failed and as part of the judgment the Texas Board of Professional Engineers noted he did not perform a geotechnical study ("no geotechnical or soil tests").

2012: S.P. of San Antonio, Texas, had engineering license suspended two years and was fined $2,000 by the Board for certifying (signing off) on incorrect as-built information.  A foundation repair plan consisting of 43 drilled piers and 5 footings was certified as completed by the engineer.  A partial collapse led to the discovery that only 34 piers and 4 footings were installed.  The engineer also had provided a drawing showing the locations of the 34 piers without association to a signed and sealed letter or plan (i.e. it should have been labeled a preliminary drawing at best).  The board determined that the engineer's cert was misleading and his actions not careful or diligent, and he issued a drawing without a seal but also without the alternative preliminary designation.

2012: A.G. of San Antonio, Texas, was suspended 2 years and fined $1,500 for issuing a misleading certification letter, allowing foundation construction that was not per city code, and not being careful or diligent in his engineering practice.  He certified a foundation repair as-built condition as meeting city code for 14-inch deep pier-footings, but city code requires minimum 24-inch deep footings.

2012: A Structural Engineering firm (Strand Systems) and Builder (Ramer Concrete) were sued by a homeowner for a distressed foundation slab (and home?).  The homeowner was able to sue without a Certificate of Merit because the claim apparently was that the Structural Engineer did not perform a "pre-pour" inspection as he was contractually obligated to do so.  Lesson: Pre-pour inspections are important and must be thorough (in this case slab thickness was too shallow) and should always be done, especially if you commit to do it in contract language.

2005: C.P. of Spring, Texas, was fined $1,500 for displaying a lack of knowledge of local codes and regulations within the locale of the project, and this lack of knowledge led to multiple submittals and delays for his client.

2005: G.H. of Amarillo, was fined $1,500 and suspended for 1 year for lack of care and diligence in reviewing a plan sheet prior to sealing and signing, and for not including his company title block on the plan sheet.  The plan sheet included designs that had nothing to do with him, so he should not have signed it.

2005: K.S. of Lake McQueeney, Texas, was suspended 2 years and fined $3,800 for providing a pre-pour inspection letter (also referred to as a certification letter whether you like it or not) that did not indicate discrepancies that another individual found at the site (rebar size, rebar layout).

2004: T.O. of Austin, Texas, was suspended 3 years and fined $3,000 for an error or omission regarding structural loading calculations which when measured by accepted standards indicated his engineering for this project was not performed in a competent manner.  The errors led to concrete columns cracking during construction which led to delays and cost overruns.

2004: J.C. of Plano, Texas, was suspended 2 years and fined $1,850 for falsely certifying that a foundation has been designed in accordance with PTI standards and soil data for conditions at the site.  However, it was discovered that the soil data was from a different site, the geotech report referenced in his plans were for a site in a different part of the subdivision (= if you think you can just use geotech soil data from another block in the subdivision you are being reckless).

N.C. of Canyon Lake was fined $500 and formally reprimanded for failing to personally verify drilled shaft depths for piers under a house.  N.C. was an expert witness in a case and his statements concerning pier depths were considered misleading.

W.L.P. of Plano, Texas, was fined $4,000 and suspended 2 years for submitting a structural design for a post-tensioned foundation slab for a custom house that ultimately did not perform well.  The design was supposedly based on PTI method, but the geotechnical report used for the basis of his design was for a lot several blocks away and performed 19 months earlier.  W.L.P. admitted the slab was underdesigned for the actual soil conditions later exposed at his site.  To top it all off, W.L.P. had a conflict of interest for being both the Structural Engineer and the partial owner of the concrete company.

M.P. a Structural Engineer in Dallas, Texas, was fined $5,000 and suspended 2 years for providing a foundation slab design based on PTI, but he did not base his design on a site-specific geotechnial report (as required by PTI).  His design was deemed misleading and not in keeping with generally accepted engineering standards or procedures.  In addition, he signed and sealed the plans for another firm based on what was on the title block, and he had not notified the Board of his association with the other firm (you can list a second firm on your Board profile).

W.S.A. of Austin, Texas, was formally reprimanded and fined $500 for failing to use site specific geotechnical soil study to prepare a residential foundation design.  Statements on the plan sheet that the design was based on unconfirmed assumptions about the soil's stability were misleading and not in keeping with generally accepted engineering practices.

W.J.R. of Laredo was fined $500 and ordered to cease and desist from practicing engineering.  W.J.R. prepared geotechnical reports that included engineering recommendations for foundation options, but W.J.R. was not a licensed PE.  (watch out for geotech letters or reports from non-PE's, this is a reckless violation of state code).

D.L.J. of Kingsbury, Texas was fined $1,250 and formally reprimanded for signing and sealing inspection letters involving inspections performed by coworkers (i.e. technician).  The inspections apparently expressed false information concerning type of existing foundation and depth of piers installed.  D.L.J. was fined because he did not provide "adequate direct supervision" over his employees, or review the inspection letters adequately, or inspect the site himself.

D.P. of Dallas, Texas, was fined $1,000 and formally reprimanded for affixing his PE seal to structural plans prepared by an employee of his part-time business.  Although D.P. had discussions with the employee and directed him to prepare the design, he was not personally present during the employee's performance of the design.  D.P. was deemed to have not provided direct supervision over his employee during the performance of the design, which is required in Texas.

M.G. of Friendswood, Texas was fined $2,000 and ordered to cease and desist from using the term "engineer" in any title or marketing literature and from practicing engineering.  M.G. identified himself as a "consulting engineer" in a residential inspection report, but M.G. did not have a PE license.

B.D.J. of Rockwall, Texas, was fined $3,000 and suspended 2 years for producing a misleading report and certification, for not conducting his inspection of a residence in a careful and diligent manner, and for actions contrary to generally accepted standards and procedures.  B.D.J. was criticized for not keeping appointments with the homeowner and members of the repair crew stated they never saw B.D.J. at the site (failed to perform inspection).  The Engineer was also noted to have not performed a slab elevation survey to help justify repair recommendations.  The Engineer was also noted to have not realized repair work was going to damage the patio addition but should have provided recommendations to avoid such damage.

J.E.C. of Fort Worth, Texas, was ordered to cease and desist from practicing structural engineering (suspended 5 years).  It was alleged that during his testimony as an expert witness in a lawsuit he made statements regarding the effect of pier to beam contact and foundation level tolerances that appeared to be misleading and were not supported by adequate modeling, calculations, or analysis and without fully disclosing the basis and rationale for his opinions.

R.W.P. of Houston was reprimanded for taking 4 months, 8 months, and 9 months to deliver residential inspection reports for 3 sites after an inspection was completed.  The reports also contained errors (misleading reports).

N.L.S. of Houston was fined $940 and suspended 9 months for signing/sealing a geotechnical report written by an individual (as another company or legal entity) who was not a PE nor a formal employee or employer of the Engineer.  This is deemed aiding and abetting an individual (and company) in the unlicensed practice of engineering.








Friday, September 21, 2012

Limit of Liability clause can actually work

Terracon was recently sued in federal court by Thrash Commercial Contractors.

Terracon was the testing lab for large fill masses being placed for a Mississippi site and apparently the testing frequency was inadequate and the General Contractor was forced by the Owner (a government agency) to remove the upper 6 feet of fill and re-install, and remove some concrete footings that were already constructed on the fill.  A study had been performed to evaluate the fill and the conclusion was that parts of the fill were not properly compacted.  Thrash sued Terracon for $300,000 in damages.  Of course the Contractor claimed Terracon had poor oversight, and Terracon claimed the Contractor did not properly schedule inspections.

The case ultimately turned to the limit of liability clause in Terracon's contract.  The testing lab fee was $14,900, and the limit of liability was $50,000.  So Terracon fell back on this position and would not pay the $300,000.  The court recognized the following:

(1) Was the contractor free to negotiate for a higher L.O.L.?  YES !  Terracon had a statement stating the client could negotiate a higher L.O.L. for an additional fee.  The contractor did not negotiate (ask) for such an increase.

(2) Was the amount of the L.O.L. reasonable relative to the fee?  For a $14k fee, $50k in liability was deemed reasonable.

(3) Were there any conflicting provisions in the contract?  The indemnity clauses protected Terracon from any negligence or omissions by the Contractor.

(4) Did the Terracon contract seek to indemnify even for its own errors?  No.

So Contractor had no case on all 4 counts and lost the case for anything more than potentially $50k in damages (not the $300k sought).

I have since reworded our company's contract language :)

Saturday, January 7, 2012

Met Cntr Bldg 10 Failure

A lawsuit concerning Met Center Bldg 10 in Austin, Texas, was settled, with the new owner being paid $1,000,000 by the project team (developer, contractor, structural engineer, and architect) including the geotechnical firm Reed Engineering. Soil movement appears to have caused extensive cosmetic and functional damage to the 350,000 square foot building. An 18-ft deep cut-off wall appears to be the plan to serve as a moisture barrier, in addition to some drainage improvements.  Did the contractor or civil/structural plans not follow geotechnical recommendations?  Or was the geotechnical report providing reckless or inadequate recommendations?